Clara Byrd Elementary School Safe Route to School (SRTS) Project

Install sidewalks, ramps, and pedestrian improvements to improve access to the school from nearby neighborhoods – September 2023


Scope of Work

Install new sidewalks, ADA ramps and pedestrian improvements in vicinity of school.

Schedule

  • Design – Fall 2021
  • Right-of-Way and Easement Acquisition – Spring 2022
  • Advertise Project – Summer 2022
  • Award Project – Fall 2022
  • Construction – Spring/Summer 2023
  • Notice to Proceed to Construction given on 1 May 2023

Budget

  • Estimated Total Project Cost: $499,011
  • Design Cost: $99,103 - 100 % complete
  • Right-of-Way Cost: $81,100 – 100% complete
  • Construction Cost: $515,195.00 – Henry S. Branscome, LLC

Milestones

  • Project Advertised June 2022
  • Project Awarded on October 27, 2022
  • Construction Started 1 May 2023
  • Construction Completed on Aug 24th 2023

Next Steps

  • Final Pay Application processing
  • Project Closeout

Project Issues

  • None