Scope of Work

The James City County irrigation and field renovations project will restore the two multipurpose fields at the Rec Center back to original specifications, promoting proper stormwater drainage, improved playability and aesthetics. This project includes the revitalization of the existing soils to a depth of 5 inches. Amendments will be added to Field 2. A computer operated irrigation system will be installed to reduce water usage on each of the two multipurpose fields. Both fields will be vegetated by a new, aggressive, wear tolerant, reduced water needs hybrid Bermudagrass.

Schedule

  • Design/Bidding - Spring 2019
  • Construction - June 2019
  • Completion - August 2019
  • Percent completed - 95%

Budget

  • Lazer grading of existing soil, additional soil, irrigation system, Bermudagrass vegetation - $147,382.00

Milestones

  • Contractor was awarded contract after Board of Supervisors approval - May 2019
  • Rough grade of field began - June 2019
  • Irrigation system installed - June 2019
  • Final grade completed - July 2019
  • Field 2 vegetative sprigged - July 2019
  • Field 1 sod installed - July 2019
  • Flail mowing of Field 2 - July 2019
  • Fertilization of Field 1 and 2 - July 2019

Next Steps

  •  Final leveling of valve boxes and irrigation heads, add vegetation to these areas - August 2019
  • Fields scheduled for opening - September 2019