- Home
- Government
- Departments
- General Services
- Capital Projects
- Completed Projects
- Toano Stream Restoration
Toano
Stream Restoration - January 2022
Scope of Work
This project involves restoring a stream channel that receives drainage from the Toano area just below the intersection of Richmond Road and Forge Road. The stream is currently unstable and eroding. The goal of the project is to restore this degraded stream and improve water quality in the watershed. The project involves restoring approximately 900 feet of stream channel using natural stream channel design techniques and replacement of a culvert under Depot Street. The project is being partially funded by a grant from the Virginia Department of Environmental Quality’s Stormwater Local Assistance Fund.
Schedule
- Complete Engineering Design – Winter 2020
- Bidding Phase – Summer 2020
- Initiate Construction – Winter 2021
- Project Completion – Spring 2021
Budget
- Estimated Budget - $1,130,000
- A. Morton Thomas and Associates, Inc. (final design contract) - $89,610.00
- Contract payments and percent completed (final design contract) - $89,610.00 – 100%
- HGS, LLC – Construction - $359,212
- Contract payments and percent completed - $341,251.40 – 95.0%
Milestones
- Stormwater Local Assistance Funds awarded July 2017
- Community Meeting Held August 2, 2018
- Concept Plan completed
- Wetlands Joint Permit application submitted May 29, 2019
- Site plan submitted for review July 24, 2019
- Site plan was approved on August 21, 2020
- All easements have been obtained for the project
- Wetlands permit received from the Army Corps of Engineers on March 30, 2020
- Bids were received from three contractors on September 11, 2020
- Projected awarded to HGS, LLC at the October 13, 2020, BOS meeting
- Notice to Proceed issued to HGS, LLC on January 4, 2021
- Stream work began on January 11, 2021
- Installation of culvert under Depot Street complete
- Stream work complete
- Wetlands and riparian plantings installation completed on April 26, 2021
- VDOT accepted the culvert replacement under Depot Street - November 4, 2021
- Final inspection held November 9, 2021
Next Steps
- Final re-stabilization of portions of the staging area and warranty inspection
Project Issues
- Easements needed to be obtained from private property owners
-
General Services
Physical Address
113 Tewning Road
Williamsburg, VA 23185
Phone 757-259-4080Fax 757-258-1528
Hours
Monday - Friday
7:30 a.m. - 4:30 p.m.