Hospital Space Renovation - April 2019


Scope of Work

Renovate the current cardio room and the space previously occupied by Sentara at the James City County Recreation Center to accommodate a new stretching area, a personal training room, a yoga studio, and a newly relocated and expanded cardio room.

Status of Project

  • In Construction

Schedule

  • Complete Final Design - December 2018
  • Advertisement for Bids - December 2018
  • Board Approval - February 2019
  • Initiation of Construction - March 2019
  • Project Completion - August 2019

Budget

  • Professional Services - $33,000
  • Construction - $195,000

Milestones

  • Initial Recreation Center patron input
  • Conceptual drawing by RRMM
  • Complete set of A&E drawings

Next Steps

  • Construction

Projects Issues

  • None