Toano Area

Drainage and Roadway Improvements - April 2019

Scope of Work

This project involves bicycle, pedestrian and drainage improvements on Richmond Road beginning at Forge Road and ending just before Toano Middle School for a total length of 0.48 miles. Improvements include the addition of a landscaped median with pedestrian refuges, sidewalk and ADA ramp improvements, crosswalks, striped bike lanes on each side of the road, and storm drainage improvements. The project addresses inadequate drainage by the installation of a parallel drainage system and additional inlets to drain existing isolated low points. Virginia Department of Transportation (VDOT) Revenue Sharing funds will be received in July 2018 to help fund the project.

Stormwater and Streetscape Improvements Map

Schedule

  • Complete Engineering Design – August 2019
  • Bidding Phase – December 2019
  • Initiate Construction – April 2020
  • Project Completion – September 2021

Budget

  • Estimated Budget - $1,287,651
  • A. Morton Thomas and Associates, Inc. (final design contract) - $79,938.11
  • Contract payments and percent completed (final design contract) - $0.00 - 0%

Milestones

  • Application submitted for VDOT Revenue Sharing funds – October 30, 2017
  • Revenue Sharing Funds awarded July 2018
  • Community Meeting held August 2, 2018
  • VDOT Rev Share Agreement Completed
  • 30% Plans submitted to VDOT for comment

Next Steps

  • Identify and obtain environmental permitting requirements
  • Identify easement requirements and utility conflicts
  • Complete final design based on comments from agencies
  • Acquire easements as required
  • Advertise project for bidding
  • Award Project
  • Construction

Project Issues

  • None